A site selector reviewing a tier-3 city's industrial parcel does not start with the parcel. The selector starts with the file. The first question the file must answer has nothing to do with acreage, zoning, or utility capacity.
It is about control. Who owns this land. Who can commit it to a project. What document proves the commitment exists.
A parcel without demonstrated site control is not a site. It is a location with attributes that may or may not be available when a prospect needs them. Selectors treat uncontrolled parcels the way they treat unverified utility capacity: as an unbounded question that eliminates the site before its physical merits get evaluated. A selector working a 90-day timeline cannot recommend a finalist where the land transaction itself is unresolved. Every open question about availability, price, or development authority adds months the project clock does not have.
This is where tier-3 cities lose deals they could win. The parcel has the right attributes. The file reveals the EDO cannot deliver it. The director may know the landowner is willing. May have had the conversation. May have a handshake understanding. None of that survives first-cut screening. The gap between what the director knows and what the director can document for a screening response is the gap where deals die. What survives is a document with a signature, a price, and a term.
The Program Standard Is the Screening Standard
State certified-site programs define what a site-selector-ready file contains. Their checklists are not aspirational. They represent the documentation threshold that separates a characterized site from a location with a marketing sheet.
On site control, the programs are explicit about acceptable forms. They also impose minimum thresholds that determine whether a parcel is even eligible for certification.
SiteOhio requires a minimum of 30 acres and "community control through ownership or option agreement and/or letter from willing owner with determined sale price per acre and mineral rights transfer." Three acceptable control forms, named.
Select Tennessee requires a minimum of 20 acres and a dated property-owner letter stating the property is for sale, naming the asking price or lease price in dollars per acre, signed by the legal owner of record or legal representative. The property must remain available for at least three years after certification. Tennessee also requires a current deed, a title search covering at least 50 years, a tax map, and a landowner-signed Voluntary Real Property Disclosure Form.
FAST NY requires ownership or control of the site, or written consent from the ownership entity and, if different, the legal-control entity. Non-municipally owned properties require a Site Control Affidavit. The program also requires a letter of support from the chief executive or a legislative resolution from the municipality with land-use authority. FAST NY's Track A checklist specifies the study scope: Phase I and/or Phase II ESA, site plan and boundary survey map, soil survey map, preliminary stormwater management plan, traffic-impact review, and wetland avoidance/minimization planning with pre-application meetings with USACE and DEC. Track A is explicitly framed as addressing major permitting issues before a business expresses interest. That makes it the most aggressive pre-permitting program among the four.
VBRSP uses a tiered system. At Tier 1, the owner agrees to market the site and allow access for assessment. By Tier 2, the program requires an option agreement or documentation of a private-owner commitment to a competitive sales price. For Site Development funding on privately held sites, a signed performance agreement between the locality and landowner must cover marketing commitment, access for development, and a maximum per-acre price for a defined period.
The common thread across all four: a site selector can verify control from the file. The evidence is a document, not a relationship.
Four Landowner Types, Four Constraints
The EDO's preparation authority differs fundamentally by who holds the land. Each situation imposes different constraints on what can be assembled before a prospect exists.
Municipal industrial park. The city owns the parcel. The EDO has maximum authority. Surveys, environmental studies, geotechnical borings, utility extensions, grading, access road construction can all be authorized through the normal municipal capital process. The site-control document is the deed. The constraint is funding, not authorization. Every element of a certified-site checklist can be initiated without a counterparty conversation. The capital budget competes with every other municipal priority, but the path from decision to drill rig is internal.
Private family or estate. The most common situation in tier-3 markets. Also the most constrained. The landowner may be willing in principle but has not committed to a price, has not granted access for studies, and may not understand what the studies involve or cost. The EDO cannot authorize a Phase II environmental investigation on someone else's land. It cannot commission a boundary survey without the owner's cooperation. It cannot file for a wetland delineation permit without site access. The authorization boundary is nearly total for any work requiring physical presence on the property. It extends equally to legal commitments only the owner can make: price, terms, availability period, mineral rights. What the EDO can do independently is limited to public records and third-party data. Zoning confirmation, flood-zone mapping, utility-capacity letters from the provider, commute-shed labor analytics, desktop environmental database review.
Developer-controlled parcels. A developer who has acquired or optioned multiple parcels for industrial development is a fundamentally different counterparty. The developer's business model depends on moving sites to market. Incentives align. The developer has typically commissioned some studies, may have completed grading or utility stub-outs, and can authorize access and commit to price without the deliberation cycle a family owner requires.
The constraint shifts from authorization to documentation alignment. The developer may have completed studies under different scopes or standards than the certification program requires. A geotechnical report commissioned for internal due diligence may not meet Select Tennessee's specification of 8 borings for 30-49 developable acres or 10 borings for 50-99 acres at an average depth of 35 feet. The EDO's job here is gap analysis against the program checklist.
The formalizing documents are specific. The developer signs the willing-owner letter (SiteOhio), the owner letter with price, terms, and three-year availability commitment (Select Tennessee), or the Site Control Affidavit (FAST NY). The developer authorizes the EDO to submit the site for program certification. Where existing studies fall short of program scope, a data-sharing agreement or MOU establishes which party funds the supplemental work, who holds the resulting reports, and whether the developer's proprietary site data can be disclosed to the certifying body. Without that agreement in writing, the EDO cannot verify that existing studies meet program requirements. The certification application stalls on a gap the developer could close in weeks.
Legacy manufacturer with surplus acreage. A plant that has contracted its footprint and sits on 40 or 80 surplus acres presents a hybrid problem. The manufacturer controls the land but is not in the business of selling it. Environmental liability dominates the conversation. The manufacturer's legal team will resist any study that might generate a documented recognized environmental condition before a remediation strategy is in place. Phase I ESA findings on a parcel adjacent to active industrial operations carry litigation risk that counsel will flag immediately.
The EDO's leverage is limited. The productive path is usually a structured conversation about the manufacturer's disposition timeline, environmental insurance, and willingness to enter a purchase option with defined liability allocation. This is a legal negotiation, not a site-readiness exercise. It requires counsel on both sides before the first boring is drilled.
The Bright Line
Every certified-site checklist contains elements on both sides of a line. The line determines whether the EDO can build the file now or needs a landowner conversation first.
Compilable without landowner involvement:
- Zoning confirmation from local code
- FEMA flood-zone determination
- Tax parcel maps from the assessor
- Utility-capacity letters from the serving provider, which the EDO can request directly
- Desktop environmental database searches
- Historical aerial photography and Sanborn maps
- SHPO desktop correspondence
- USFWS desktop species review
- Commute-shed labor analytics from OEWS and IPEDS data
- Traffic counts from state DOT
- Rail-proximity verification from public mapping
These are real assets. A file that contains all of them is materially stronger than one that contains none. But they are not sufficient for certification in any of the four programs examined here. Every program requires studies that demand physical access to the parcel.
Requires landowner authorization for site access:
- Phase I ESA involves visual inspection of the property and structures. ASTM E1527-21 identifies the site reconnaissance as a component that must be completed or updated within 180 days. The standard allows a limited alternative when access cannot be obtained after good-faith efforts, but a Phase I completed without site access is a weaker document. A selector will note the limitation.
- Phase II ESA requires subsurface sampling: soil borings, groundwater monitoring wells, media analysis. No landowner authorization, no Phase II.
- Geotechnical study requires borings on the parcel at program-specified depths and densities.
- Wetland delineation requires field assessment following the 1987 Corps Manual and appropriate Regional Supplement. SiteOhio requires USACE Approved Jurisdictional Determination. Select Tennessee requires agency concurrence from TDEC and USACE.
- Boundary and topographic survey requires crews on the property. VBRSP Tier 3 specifies a one-foot topographic survey signed and sealed by a Virginia-licensed professional.
- FAST NY Track A requires the boundary survey map and wetland avoidance/minimization planning with pre-application meetings with USACE and DEC. All of which presuppose authorized site access.
Requires landowner legal commitment:
- Purchase option with defined price, term, and conditions
- Willing-owner letter with price per acre and, in Ohio's case, mineral-rights transfer language
- Written consent to funding application (FAST NY requires this from both ownership and legal-control entities)
- Utility easement grants for service extension across private land
- Performance agreement with locality (VBRSP requires this for Site Development funding on privately held parcels)
- Availability commitment for a defined period (Select Tennessee requires three years post-certification)
The Financial Ask
Someone pays for the studies that require site access. Who pays is often where the conversation stalls.
The following ranges reflect current market pricing from environmental and surveying industry cost guides for industrial parcels in the 30-100 acre size class. These are practitioner budgeting ranges, not program-published figures. Actual procurement costs vary by region, site complexity, and prior use.
| Study | Budgeting Range |
|---|---|
| Phase I ESA | $4,000–$6,000+ for industrial sites or multiple parcels |
| Phase II ESA | $5,000–$35,000 (limited-to-moderate scope); $35,000–$100,000+ (complex or large industrial sites) |
| ALTA/NSPS boundary survey (20+ acres) | $25,000–$50,000+; difficult access adds 25%–100% to base cost |
| Geotechnical study at certification scope | Low-to-mid five figures (8–10 borings at 35 ft per Select Tennessee specs); generic two-bore reports at $1,000–$5,000 do not meet program requirements |
| Wetland delineation with cross-agency coordination (20+ acres) | $15,000–$28,000+ |
A 50-acre greenfield parcel can reach $75,000–$150,000 before any grading, utility extension, or access-road work begins.
State site-readiness grants offset some of this. Tennessee's Site Development Grants fund due diligence studies. VBRSP Site Development grants fund work to advance a site toward Tier 5. FAST NY Track A funds pre-permitting work explicitly. But grant applications themselves require demonstrated site control. The EDO is back at the landowner conversation.
The structure of the cost-share matters. A willing-owner letter is easier to obtain when the EDO can say: the state grant covers 80% of the Phase I and geotechnical, and we need you to grant access and sign the consent form. That is a materially different ask than $100,000 in studies on a parcel that may or may not attract a prospect.
The Tier Ladder as a Planning Framework
Virginia's tier system is useful beyond Virginia because it makes the progression explicit.
Tier 3 is the due-diligence base: zoning, wetlands delineation with USACE approval, geotechnical borings, boundary survey, topographic survey, cultural resources review, threatened and endangered species review, Phase I ESA, and floodplain or karst evaluation where applicable. Tier 3 also requires master planning and preliminary engineering with estimated costs and timelines.
Tier 4 adds a schedule commitment. Building construction can begin within 12-18 months. Infrastructure plans must be completed, approved, and deemed deliverable within that window by a Virginia-licensed Professional Engineer.
Tier 5 is shovel-ready. Construction can begin as soon as land-disturbance permits are obtained. Utilities are at the site or extendable in less than 12 months.
The jump from Tier 3 to Tier 4 is where most tier-3 cities stall. It requires a licensed engineer's certification that infrastructure is deliverable on a defined timeline. That certification depends on utility commitments, permitting pathway confirmation, and funded capital plans. It also depends on the landowner. The engineer cannot certify a deliverable timeline if the landowner has not committed to continued access for additional engineering work, has not agreed to hold pricing during the infrastructure build-out period, or has not executed the performance agreement that VBRSP requires for Site Development funding on privately held parcels.
The studies reduce uncertainty. The commitments from the utility and the landowner convert the site from characterized to competitive. Those are different stages, and the second one requires the landowner's signature.
The Deferred Conversation
Every element on the landowner side of the bright line requires a conversation that many EDOs have not had. The deferral makes sense on its own terms. Approaching a private landowner about industrial development involves price expectations, environmental liability concerns, timeline uncertainty, and the possibility that the landowner says no. It is easier to compile the public-record elements, build a marketing sheet, and wait for a prospect's interest to motivate the landowner.
That sequence inverts the screening process. The file review happens before the prospect visits. If the file shows an uncontrolled site, there is no visit.
The foundational move is a pre-negotiation meeting that establishes three categories: what can be stated publicly about the site's availability, what can be shared under NDA with a qualified prospect, and what requires a project-specific negotiation. The landowner is a counterparty whose pre-clearance determines what the EDO can put in the file.
SiteOhio's willing-owner letter with a determined sale price per acre is the minimum viable document. Select Tennessee's owner letter with price, terms, and three-year availability commitment is stronger. VBRSP's performance agreement with marketing, access, and price commitments is the most comprehensive. They represent a progression in landowner engagement, and each level produces a correspondingly more credible file.
The parcel's physical attributes are the same in all three cases. The file's ability to prove the EDO can deliver them is not.
- SEEDS Round 4 open: Alabama's SEEDS program is accepting applications through August 31 for approximately $11.7 million in site-assessment grants, requiring site ownership or purchase option and at least 50 acres.
- Tennessee site development grants: TNECD announced 10 Site Development Grants totaling more than $13 million on June 30, funding infrastructure and engineering improvements tied to Select Tennessee certification.
- PA SITES Round 3: Pennsylvania's February 2026 awards of more than $31 million across seven projects included earthwork, utility-pole relocation, and asbestos-contaminated building demolition, illustrating how state readiness programs are funding physical site conversion, not just studies.
- FAST NY cumulative scale: Empire State Development reports combined FAST NY awards exceeding $333 million for 44 projects covering nearly 8,800 acres, including 4,775 infrastructure-improved developable acres, making it the largest pre-permitting site program among the four examined here.

